The Project

Funder: Ontario Trillium Foundation

Project Website: https://workinculture.ca/

Duration: June 8, 2022 to April 30, 2023

Goals

Collaboratively design a new version of the WorkInCulture job board and web site with a community-led co-design approach so it can be implemented by the system builder.

Co-Design

Who should be involved? Who are the people who will be impacted by the design of the job board and the website?

  1. WIC community of jobseekers
  2. People who want to, but never used WIC’s job board
  3. Employers - those who post jobs to the board
  4. Administrators - those who are responsible for maintaining the website and content
  5. WIC funders
  6. System builder - Surface Impression

Also see: WIC Co-design Planning

Tasks

  • identify needs and priorities for the new site, and to examine supports that may enable greater impact and benefit for marginalized groups, including the gathering of metrics and data that will support more inclusive hiring practices.
  • Lead two co-design workshops to engage the community in helping to design and refine the website and the job board
  • Synthesize and summarize the results of the co-design workshops
  • Design user flows, user interface wireframes, and other specifications useful for the development of the site
  • Create visual and/or interactive mock-ups of the user interface
  • Solicit feedback on the designs and platform through participatory design ‘crits’ and feedback sessions

Deliverables

The IDRC at OCAD U will provide WorkInCulture with:

  1. A synthesis of the results from the co-design workshops after the completion of codesign.
  2. Medium-fidelity user interface mock-ups that a web development firm can use to implement the final design.

Documents and Resources

  • WorkIn Culture Job Board
  • Design framework for another project - Bodies in Translation
  • 2018 surveys from WIC
    • Located on nextcloud > IDRC-Design > Projects > WorkIn Culture > WIC Job Board Survey 2018
  • Meeting notes
  • Subaward document between IDRC and OTF - Includes Appendix B.
    • Located on nextcloud > IDRC-Design > Projects > WorkIn Culture
  • Surface Impressions Quote - they are building the website
    • Located on nextcloud > IDRC-Design > Projects > WorkIn Culture

IDRC will use the following existing infrastructure for their ongoing work and digital asset storage:

  • Fluid Wiki for public information
  • IDRC Nextcloud for working docs and reports
  • OCADU OneDrive / SharePoint for sensitive information
  • Figma for mockups

Timeline

January

TaskWhoStatusNotes
Share synthesis reportIDRC

Mid-January

Should have all major components present:

  • Findings from co-design - Needs, ideas, aspirational goals
  • Priority features including mockups / design guidance
  • Guidance on inclusion and web accessibility
  • Guidance on future direction and opportunities
  • continue to refine over time
Check-in with advisory panelIDRC, WIC, SI

Share progress and get panel feedback.

December

TaskWhoStatusNotes
Report job poster interview findingsWIC

Refine mockups and userflows for feature set based on Job Poster feedbackIDRC

Refine and firm up details on priority featuresWIC, SI, IDRC

Continue development on websiteSI

November

TaskWhoStatusNotes
Share initial findings from workshopsIDRC

Status
colourGreen
titleDone

Early November
Synthesize findings and create feature listIDRC

Status
colourGreyGreen
titleIN progressDone

Early-mid November
Scope and prioritize website feature setWIC, SI, IDRC

Status
colourGreen
titleDone

Mid November
Build back-end functionalitySI
Mid-late November
Finalize job poster interview questions based on feature setWIC, IDRC
Mid November
Job poster interviewsWIC
Late November
Refine mockups and userflows for feature setIDRC
Late November

October

TaskWhoStatusNotes

Co-design session 1

IDRC

Status
colourGreen
titledone


Co-design session 2


Status
colourGreen
titledone


September

TaskWhoStatusNotes
Actively recruit for co-design
IDRC, WIC

Status
colourGreen
titledone

Send invitations with registration form links

Select participants for Co-design by Sep 19

Status
colourGreen
titledone


(Cont'd) Discovery conversations with WIC staff

Status
colourGreen
titledone


Discovery conversations with job posters


Objective: 4 to 8 interviews


August

TaskWhoStatusNotes

Plan co-design workshops

IDRC

Status
colourGreen
titledone


Prepare for co-design recruitment

IDRC, WIC

Status
colourGreen
titledone

Identify people and orgs to contact.

Prepare email templates, registration form, CLA, media release, consent forms

Send out call for interest

IDRC, WIC

Status
colourGreen
titledone


Receive ethics clearance

IDRC

Status
colourGreen
titledone


Discovery conversations with WIC staff


Status
colourGreen
titledone

Questions to answer:

  1. What went well?
  2. What didn't go well? What causes difficulty or friction? How would you do it differently?
  3. If you could do it better, what would it be like?

July

TaskWhoStatusNotes

Revise / Finalize REB

IDRC

Status
colourGreen
titleDONE


Begin planning co-design session 1

IDRC, WIC

Status
colourGreen
titleDone

See: WIC Co-design Planning

Begin REB approval process

IDRC

Status
colourGreen
titleDONE


Draft Survey for job seekersIDRC, WIC

Status
colourGrey
titleNot doing

Instead of survey, focus on co-design.

See survey planning wiki page.

Draft / prototype survey created in Google Forms.

June 2022

TaskWhoStatusNotes
Formulate draft timelineIDRC

Status
colourGreen
titleDONE


Decide on project coordinationIDRC, SI, WIC

Status
colourGreen
titleDONE

Meetings every 2 weeks or as needed

Draft REB applicationIDRC

Status
colourGreen
titleDone

Draft is complete. Awaiting review before submission.
Finalize timelineIDRC, SI, WIC

Status
colourGreen
titleDone

Done for now