January

WK 1:  3-9

  • Meet with Xiao introduce FE project orientation and set up all communications channels. (VM, LA, XZ)
  • Weekly correspondence with FE team, standup and design team meetings. (VM, LA, XZ)
  • Build a work plan for the physical design of the kiosk including hardware, placement, accessibility concerns and touch screen options. (VM)

...

  • SFU weekly meet and workflow check-in.
  • Weekly correspondence with FE team, standup and design team meetings.
  • Review kiosk research, select options, review senarios on this wiki page http://wiki.fluidproject.org/display/fluid/Map+tool+overview+and+scenarios. (VM)
  • Review the types of kiosks with the design team and select options. (FE Design Team)
  • Review options with DIA and confirm kiosk options. (Jess and James)
  • Conduct industry review on the various touch screen options and deign requirements. (XZ)
  • Update WIKI with new information



February

WK5: Jan 31 – Feb 6

  • SFU weekly meet and workflow check-in.
  • Weekly correspondence with FE team, standup and design team meetings.
  • Update WIKI with meeting notes.
  • Write up recommendations and illustrations ideas for best solutions inline with senarios. (VM, XZ, LA)
  • Discuss recommendations with design team – select direction.

...

  • SFU weekly meet and workflow check-in.
  • Weekly correspondence with FE team, standup and design team meetings.
  • Investigate haptic requirerments.
  • Map infrastructure requirerments.
  • Update WIKI with new information


March

WK9: Feb 28 – Mar 6

  • SFU weekly meet and workflow check-in.
  • Weekly correspondence with FE team, standup and design team meetings.
  • Build kioks prototype maybe 2-weeks.
  • Develop a participatory test plan for evaluating the physical kiosk designs.
  • Update WIKI with new information

...