Story Title | Estimate |
---|---|
Contextual Inquiry - Toronto faculty 2 (2 UX team members) | 1.25 days |
Contextual Inquiry - Toronto faculty 3 (2 UX team members) | 1.25 days |
Contextual Inquiry - Toronto faculty 4 (2 UX team members) | 1.25 days |
Contextual Inquiry - Toronto faculty 5 (2 UX team members) | 1.25 days |
Contextual Inquiry - Berkeley faculty 1 (2 UX team members) | 1.25 days |
Contextual Inquiry - Berkeley student 2 (2 UX team members) | 1.25 days |
Contextual Inquiry - Berkeley student 3 (2 UX team members) | 1.25 days |
Contextual Inquiry - Berkeley student 4 (2 UX team members) | 1.25 days |
Create notes summary template and description of process | .5 days |
Create wiki page describing planning process & guidelines | .5 days |
Revise Portlet Layout Manager Customizer protocol for user test | .25 days |
Revise questionnaires for Portlet Layout Manager Customizer user test | .5 days |
User Testing - Toronto Student 1 (1 UX team member) | .25 day |
User Testing - Toronto Student 2 (1 UX team member) | .25 day |
User Testing - Toronto Student 3 (1 UX team member) | .25 day |
User Testing - Toronto Student 4 (1 UX team member) | .25 day |
Kuali UX Lead Interviews (running total= 20.25) | 3 days |
Upload Component Design Work | 2 days |
Subtotal of Iteration Specific Activities | 17.75 |
|
|
Ongoing Activities | |
Ongoing - Sakai UX weekly meeting (Daphne, Allison, Shaw-Han, Barbara, Eli, Mike E. - 2 hrs each/each iteration) | 1.25 days |
Kuali - Maintain contact with the Kuali UX folks and offer UX advice when needed (Allison) | .5 days |
Ongoing - CI weekly processing meetings (Daphne, Allison, Shaw-Han, Barbara - 2 hrs each / each iteration) | 1 day |
Subtotal of Iteration Specific Activities | 2.75 |
TOTAL | 20.5 |
...