February 6 to February 19 UX Team Iteration Plan
Task List, Feb. 5 - Feb. 19 2008
Total days of work in this iteration: 20.5
Story Title |
Estimate |
---|---|
Contextual Inquiry - Toronto faculty 2 (2 UX team members) |
1.25 days |
Contextual Inquiry - Toronto faculty 3 (2 UX team members) |
1.25 days |
Contextual Inquiry - Toronto faculty 4 (2 UX team members) |
1.25 days |
Contextual Inquiry - Toronto faculty 5 (2 UX team members) |
1.25 days |
Contextual Inquiry - Berkeley faculty 1 (2 UX team members) |
1.25 days |
Contextual Inquiry - Berkeley student 2 (2 UX team members) |
1.25 days |
Contextual Inquiry - Berkeley student 3 (2 UX team members) |
1.25 days |
Contextual Inquiry - Berkeley student 4 (2 UX team members) |
1.25 days |
Create notes summary template and description of process |
.5 days |
Create wiki page describing planning process & guidelines |
.5 days |
Revise Layout Customizer protocol for user test |
.25 days |
Revise questionnaires for Layout Customizer user test |
.5 days |
User Testing - Toronto Student 1 (1 UX team member) |
.25 day |
User Testing - Toronto Student 2 (1 UX team member) |
.25 day |
User Testing - Toronto Student 3 (1 UX team member) |
.25 day |
User Testing - Toronto Student 4 (1 UX team member) |
.25 day |
Kuali UX Lead Interviews                                                            (running total= 20.25) |
3 days |
Upload Component Design Work |
2 days |
Subtotal of Iteration Specific Activities |
17.75 |
 |
 |
Ongoing Activities |
|
Ongoing - Sakai UX weekly meeting (Daphne, Allison, Shaw-Han, Barbara, Eli, Mike E. - 2 hrs each/each iteration) |
1.25 days |
Kuali - Maintain contact with the Kuali UX folks and offer UX advice when needed (Allison) |
.5 days |
Ongoing - CI weekly processing meetings (Daphne, Allison, Shaw-Han, Barbara - 2 hrs each / each iteration) |
1 day |
Subtotal of Iteration Specific Activities |
2.75 |
                                                                                                                                                                                           TOTAL |
20.5 |
Postponed
Design Patterns - Create Open Source Design Patterns working group charter (address how the different communities will work together on patterns) |
.5 days |
Design Patterns - Invite folks from mailing lists (sakai-ui, fluid-work, jasig-ue) to OSDP working group |
.25 day |
Design Patterns - Hold first & subsequent weekly OSDP working group meetings, review charter, allocate tasks, choose roles, plan & take next steps |
2.25 days |
Design Patterns - Catalog different ways pattern libraries handle screenshots to make case for not asking permission |
.5 days |
Design Patterns - Create OSDP Library Home page |
.25 days |
|
|
|
|
Calculations for this Iteration:
Name |
FTE Equivalent |
---|---|
Shaw-Han |
1 |
Barbara |
1 |
Allison |
1 |
Daphne |
1/2 |
Eli |
1/3 |
Paul |
1/2 |
Total: 4 1/3 FTE
Days in this iteration 8.5 (10 - 0.5 for planning and 1 holiday)
Total Person Days = 4 1/3 * 8.5 = approx 36.75
Person days from last iteration: 39
Work completed last iteration: 9.25
Velocity = work completed / person days = 9.25 / 39 = 23%
Expected work for this iteration: 36.75 * 0.23 = approx 8.5
- According to "yesterday's weather", we can get 8.5 days of work done this iteration *