February 6 to February 19 UX Team Iteration Plan

Task List, Feb. 5 - Feb. 19 2008

See Issues in JIRA

Total days of work in this iteration: 20.5

Story Title

Estimate

Contextual Inquiry - Toronto faculty 2 (2 UX team members)

1.25 days

Contextual Inquiry - Toronto faculty 3 (2 UX team members)

1.25 days

Contextual Inquiry - Toronto faculty 4 (2 UX team members)

1.25 days

Contextual Inquiry - Toronto faculty 5 (2 UX team members)

1.25 days

Contextual Inquiry - Berkeley faculty 1 (2 UX team members)

1.25 days

Contextual Inquiry - Berkeley student 2 (2 UX team members)

1.25 days

Contextual Inquiry - Berkeley student 3 (2 UX team members)

1.25 days

Contextual Inquiry - Berkeley student 4 (2 UX team members)

1.25 days

Create notes summary template and description of process

.5 days

Create wiki page describing planning process & guidelines

.5 days

Revise Layout Customizer protocol for user test

.25 days

Revise questionnaires for Layout Customizer user test

.5 days

User Testing - Toronto Student 1 (1 UX team member)

.25 day

User Testing - Toronto Student 2 (1 UX team member)

.25 day

User Testing - Toronto Student 3 (1 UX team member)

.25 day

User Testing - Toronto Student 4 (1 UX team member)

.25 day

Kuali UX Lead Interviews                                                            (running total= 20.25)

3 days

Upload Component Design Work

2 days

Subtotal of Iteration Specific Activities

17.75

 

 

Ongoing Activities


Ongoing - Sakai UX weekly meeting (Daphne, Allison, Shaw-Han, Barbara, Eli, Mike E. - 2 hrs each/each iteration)

1.25 days

Kuali - Maintain contact with the Kuali UX folks and offer UX advice when needed (Allison)

.5 days

Ongoing - CI weekly processing meetings (Daphne, Allison, Shaw-Han, Barbara - 2 hrs each / each iteration)

1 day

Subtotal of Iteration Specific Activities

2.75

                                                                                                                                                                                            TOTAL

20.5

Postponed

Design Patterns - Create Open Source Design Patterns working group charter (address how the different communities will work together on patterns)

.5 days

Design Patterns - Invite folks from mailing lists (sakai-ui, fluid-work, jasig-ue) to OSDP working group

.25 day

Design Patterns - Hold first & subsequent weekly OSDP working group meetings, review charter, allocate tasks, choose roles, plan & take next steps

2.25 days

Design Patterns - Catalog different ways pattern libraries handle screenshots to make case for not asking permission

.5 days

Design Patterns - Create OSDP Library Home page

.25 days





Calculations for this Iteration:

Name

FTE Equivalent

Shaw-Han

1

Barbara

1

Allison

1

Daphne

1/2

Eli

1/3

Paul

1/2

Total: 4 1/3 FTE

Days in this iteration 8.5 (10 - 0.5 for planning and 1 holiday)
Total Person Days = 4 1/3 * 8.5 = approx 36.75

Person days from last iteration: 39
Work completed last iteration: 9.25
Velocity = work completed / person days = 9.25 / 39 = 23%

Expected work for this iteration: 36.75 * 0.23 = approx 8.5

  • According to "yesterday's weather", we can get 8.5 days of work done this iteration *