February 6 to February 19 UX Team Iteration Plan
Task List, Feb. 5 - Feb. 19 2008
Total days of work in this iteration: 20.5
Story Title | Estimate |
|---|---|
Contextual Inquiry - Toronto faculty 2 (2 UX team members) | 1.25 days |
Contextual Inquiry - Toronto faculty 3 (2 UX team members) | 1.25 days |
Contextual Inquiry - Toronto faculty 4 (2 UX team members) | 1.25 days |
Contextual Inquiry - Toronto faculty 5 (2 UX team members) | 1.25 days |
Contextual Inquiry - Berkeley faculty 1 (2 UX team members) | 1.25 days |
Contextual Inquiry - Berkeley student 2 (2 UX team members) | 1.25 days |
Contextual Inquiry - Berkeley student 3 (2 UX team members) | 1.25 days |
Contextual Inquiry - Berkeley student 4 (2 UX team members) | 1.25 days |
Create notes summary template and description of process | .5 days |
Create wiki page describing planning process & guidelines | .5 days |
Revise Layout Customizer protocol for user test | .25 days |
Revise questionnaires for Layout Customizer user test | .5 days |
User Testing - Toronto Student 1 (1 UX team member) | .25 day |
User Testing - Toronto Student 2 (1 UX team member) | .25 day |
User Testing - Toronto Student 3 (1 UX team member) | .25 day |
User Testing - Toronto Student 4 (1 UX team member) | .25 day |
Kuali UX Lead Interviews (running total= 20.25) | 3 days |
Upload Component Design Work | 2 days |
Subtotal of Iteration Specific Activities | 17.75 |
|
|
Ongoing Activities | |
Ongoing - Sakai UX weekly meeting (Daphne, Allison, Shaw-Han, Barbara, Eli, Mike E. - 2 hrs each/each iteration) | 1.25 days |
Kuali - Maintain contact with the Kuali UX folks and offer UX advice when needed (Allison) | .5 days |
Ongoing - CI weekly processing meetings (Daphne, Allison, Shaw-Han, Barbara - 2 hrs each / each iteration) | 1 day |
Subtotal of Iteration Specific Activities | 2.75 |
TOTAL | 20.5 |
Postponed
Design Patterns - Create Open Source Design Patterns working group charter (address how the different communities will work together on patterns) | .5 days |
Design Patterns - Invite folks from mailing lists (sakai-ui, fluid-work, jasig-ue) to OSDP working group | .25 day |
Design Patterns - Hold first & subsequent weekly OSDP working group meetings, review charter, allocate tasks, choose roles, plan & take next steps | 2.25 days |
Design Patterns - Catalog different ways pattern libraries handle screenshots to make case for not asking permission | .5 days |
Design Patterns - Create OSDP Library Home page | .25 days |
| |
| |
Calculations for this Iteration:
Name | FTE Equivalent |
|---|---|
Shaw-Han | 1 |
Barbara | 1 |
Allison | 1 |
Daphne | 1/2 |
Eli | 1/3 |
Paul | 1/2 |
Total: 4 1/3 FTE
Days in this iteration 8.5 (10 - 0.5 for planning and 1 holiday)
Total Person Days = 4 1/3 * 8.5 = approx 36.75
Person days from last iteration: 39
Work completed last iteration: 9.25
Velocity = work completed / person days = 9.25 / 39 = 23%
Expected work for this iteration: 36.75 * 0.23 = approx 8.5
According to "yesterday's weather", we can get 8.5 days of work done this iteration *