Complete infrastructure tasks for January 2016 GPII Component Review

Description

Important dates:

  • January 7 (Thursday) - week of lead up to review

  • January 14 + 15 : Cloud4All Final Review

  • February: Prosperity4All face-to-face review (17th and 19th)

  • All of these are on EU time zone

Requirements:

  • one (public) instance of all GPII components

  • running reliably (zero downtime)

  • able to be rapidly updated by developers themselves

  • also critical: GPII wiki and Jira

  • better monitoring and logging

Planning document:

Environment

None
100% Done